Foundation Work |
7 July '09 |
Piling Work |
|
9 July '09 |
Concreting of Piles |
|
4 Aug '09 |
Pile Testing |
|
9 Aug '09 |
Excavation for Foundation |
|
13 Aug '09 |
Concreting of Service Block Foundation |
|
29 Aug '09 |
Finishing of Piles 1 |
|
7 Sept '09 |
Finishing of Piles 2 |
|
7 Sept '09 |
Shuttering for all the pile caps |
|
8 Sept '09 |
Pile cap casting & service block foundation 1 |
|
8 Sept '09 |
Pile cap casting & service block foundation 2 |
|
14 Sept '09 |
Shuttering & Reinforcement for tie beam all around |
|
17 Sept '09 |
Concrete Casting of ground tie beam & wall of underground tank |
|
26 Sept '09 |
Reinforcement mesh & concrete casting for ground slab 1 |
|
26 Sept '09 |
Reinforcement mesh & concrete casting for ground slab 2 |
|
26 Sept '09 |
Reinforcement mesh & concrete casting for ground slab 3 |
Structural Work |
28 Sept '09 |
Column Shuttering |
|
30 Sept '09 |
Shuttering & Reinforcement for Column (G-Floor before alignment) |
|
30 Sept '09 |
Column Concreting |
|
8 Oct '09 |
Concrete casting for column 2nd lift (ground floor) 1 |
|
8 Oct '09 |
Concrete casting for column 2nd lift (ground floor) 2 |
|
9 Oct '09 |
Shuttering of columns is removed & the curing in progress - 1 |
|
9 Oct '09 |
Shuttering of columns is removed & the curing in progress - 2 |
|
12 Oct '09 |
Curing of columns & shuttering for the staircase |
|
16 Oct '09 |
Trench for boundary wall in progress & shuttering of staircases |
|
20 Oct '09 |
Supports for the periphery beams in progress & the shuttering reinforcement for staircase first landing is completed |
|
22 Oct '09 |
Scaffolding for the receiving and periphery beams |
|
30 Oct '09 |
Reinforcement for 1st floor solid slabs are nearing completion |
|
5 Nov '09 |
Periphery beams, receiving beams scaffolding and reinforcement nearing completion 1 |
|
5 Nov '09 |
Periphery beams, receiving beams scaffolding and reinforcement nearing completion 2 |
|
9 Nov '09 |
Snaps on the day the concrete was rejected from supplier |
|
11 Nov '09 |
Casting concrete for slab and periphery, receiving beams |
|
13 Nov '09 |
Shuttering for beams removed |
|
14 Nov '09 |
Laying of hollow core slabs |
|
15 Nov '09 |
Hollow core slab of main hall ground floor |
|
18 Nov '09 |
Casting of solid slab and topping concrete |
|
5 Dec '09 |
First floor column casting |
|
18 Dec '09 |
Ground Floor Walls |
|
30 Dec '09 |
Preparation for concreting & interior walls |
|
31 Dec '09 |
Roof slab & beam casting |
|
5 Jan '10 |
Second stage concrete of roof slab |
|
15 Jan '10 |
Plastering Work in Progress |
|
16 Jan '10 |
Hollow core slabs for 1st Floor |
|
17 Jan '10 |
After laying hollow core slabs |
|
21 Jan '10 |
Topping of concrete slab |
|
23 Jan '10 |
Curing after casting of topping |
|
27 Jan '10 |
Exterior Structure & Boundary Wall |
|
31 Jan '10 |
Tiling Work in Progress |
|
5 Feb '10 |
Boundary wall, plumbing, parapet reinforcement & tiling - Pt 1 |
|
5 Feb '10 |
Boundary wall, plumbing, parapet reinforcement & tiling - Pt 2 |
|
12 Feb '10 |
Primer for painting & hollow block work (Ground floor) |
|
12 Feb '10 |
Car porch, boundary wall, Service block & Parapet |
|
22 Feb '10 |
Tiling, baptistery shuttering & reinforcement, plastering works, hollow works (in progress), wrapping of AC ducts. - Pt 1 |
|
5 Feb '10 |
Tiling, baptistery shuttering & reinforcement, plastering works, hollow works (in progress), wrapping of AC ducts. - Pt 2 |
|
5 Mar '10 |
AC duct works and foam concrete for water proofing roof slab |
|
15 Mar '10 |
AC duct, baptistery works and waterproofing for the roof |
|
26 Mar '10 |
Water proofing, AC ducting & finishing works in progress |
|
31 Mar '10 |
Light hollow block, primer painting, front window frame |
|
6 Apr '10 |
Stage for Ground & 1st floor, plastering & primer painting |
|
20 Apr '10 |
Flooring, Tiling, Painting & External works in progress |
|
25 Apr '10 |
Tiling & skirting for the main hall. Primer for service block. Plastering of outside walls. Electrical & AC ducting, Tiling, painting & external works in progress |
|
28 Apr '10 |
Roof work, false-ceiling, AC, safety & electrical works in progress |
|
7 May '10 |
Terrazo tiles on roof, fire door, painting for walls & tiling |
|
14 May '10 |
Foundation for AC units, ceiling frames, toilet tiling & primer painting |
|
20 May '10 |
Ceiling frame, infant room, primer painting on outer/inner walls, electrical & firefighting networks, AC ducts works & tiling in main hall in progress |
|
23 May '10 |
Staircase at the rear of the building, stage on the first floor, tiling in the main hall, door frames placement etc. in progress |
|
25 May '10 |
Internal painting, mock marble sample, block-work above the parapet |
|
1 Jun '10 |
Marble laying, AC ducts installation & toilet fittings in progress |
|
8 Jun '10 |
Outer Painting & False ceiling on the ground floor |
|
20 Jun '10 |
Painting, ceiling works, toilet fittings, outside baptistery in progress |
|
23 Jun '10 |
Window frames installation, AC unit installation & bulkhead works in progress |
|
30 Jun '10 |
Glass fitting for windows & bulk head work in progress |
|
27 Jul '10 |
Rear Staircase flooring, baptistery, pavement flooring & door fitting in progress |
|
30 Jul '10 |
Ceiling, hand rail installation, internal & external painting in progress |
|
6 Aug '10 |
Painting, AC setup, gate & tank placement along with other finishing works |
|
12 Aug '10 |
Tiling, ceiling work, bulk head, AC, painting, gate, front-door works in progress |
|
16 Aug '10 |
Electrical lighting fixtures for halls, granite for car porch, painting for borders in progress |
|
27 Aug '10 |
AC units installation & tiling of the stage on ground floor in progress |
|
Finishing Work |
30 Aug '10 |
Doors fixing, roof tiles painting, ground floor hall tiling in progress |
|
3 Sept '10 |
Painting & False ceiling fixing in progress |
|
5 Sept '10 |
Pasco, corniche work & 1st floor ceiling work in progress |
|
13 Sept '10 |
External painting works for main building & service block in progress |
|
13 Sept '10 |
External baptistery preparation, cupboards & 1st floor ceiling finishing in progress |
|
15 Sept '10 |
Church name fixed. False ceiling, staircase & cupboard finishing in progress |
|
23 Sept '10 |
Ceiling works completed, site-office caravan removed, painting & cleaning in progress |
|
1 Oct '10 |
Baptistery works (inside & outside), cupboards works & painting in progress |
|
8 Oct '10 |
Front Entrance, cupboards, interior finishing & external painting works in progress |
|
19 Oct '10 |
Glass fixing, painting of boundary wall columns, cleaning, cladding of AC in progress |
|
25 Oct '10 |
Initial inspection by NAFCO completed successfully for firefighting. Rooms are being cleaned. Painting for boundary wall columns in progress. |
|
4 Nov '10 |
Stage Preparation, Sound system cabling & other finishing works in progress. |
|
10 Feb'11 |
The First Lights in the BCC - Part 1 |
|
10 Feb'11 |
The First Lights in the BCC - Part 2 |
|