Foundation Work

7 July '09

Piling Work

Pictures

     

9 July '09

Concreting of Piles

Pictures

     

4 Aug '09

Pile Testing

Pictures

     

9 Aug '09

Excavation for Foundation

Pictures

     

13 Aug '09

Concreting of Service Block Foundation

Pictures

     

29 Aug '09

Finishing of Piles 1

Pictures

     

7 Sept '09

Finishing of Piles 2

Pictures

     

7 Sept '09

Shuttering for all the pile caps

Pictures

     

8 Sept '09

Pile cap casting & service block foundation 1

Pictures

     

8 Sept '09

Pile cap casting & service block foundation 2

Pictures

     

14 Sept '09

Shuttering & Reinforcement for tie beam all around

Pictures

     

17 Sept '09

Concrete Casting of ground tie beam & wall of underground tank

Pictures

     

26 Sept '09

Reinforcement mesh & concrete casting for ground slab 1

Pictures

     

26 Sept '09

Reinforcement mesh & concrete casting for ground slab 2

Pictures

     

26 Sept '09

Reinforcement mesh & concrete casting for ground slab 3

Pictures

     
 Structural Work

28 Sept '09

Column Shuttering

Pictures

     

30 Sept '09

Shuttering & Reinforcement for Column (G-Floor before alignment)

Pictures

     

30 Sept '09

Column Concreting

Pictures

     

8 Oct '09

Concrete casting for column 2nd lift (ground floor) 1

Pictures

     

8 Oct '09

Concrete casting for column 2nd lift (ground floor) 2

Pictures

     

9 Oct '09

Shuttering of columns is removed & the curing in progress - 1

Pictures

     

9 Oct '09

Shuttering of columns is removed & the curing in progress - 2

Pictures

     

12 Oct '09

Curing of columns & shuttering for the staircase

Pictures

     

16 Oct '09

Trench for boundary wall in progress & shuttering of staircases

Pictures

     

20 Oct '09

Supports for the periphery beams in progress & the shuttering reinforcement for staircase first landing is completed

Pictures

     

22 Oct '09

Scaffolding for the receiving and periphery beams

Pictures

     

30 Oct '09

Reinforcement for 1st floor solid slabs are nearing completion

Pictures

     

5 Nov '09

Periphery beams, receiving beams scaffolding and reinforcement nearing completion 1

Pictures

     

5 Nov '09

Periphery beams, receiving beams scaffolding and reinforcement nearing completion 2

Pictures

     

9 Nov '09

Snaps on the day the concrete was rejected from supplier

Pictures

     

11 Nov '09

Casting concrete for slab and periphery, receiving beams

Pictures

     

13 Nov '09

Shuttering for beams removed

Pictures

     

14 Nov '09

Laying of hollow core slabs

Pictures

     

15 Nov '09

Hollow core slab of main hall ground floor

Pictures

     

18 Nov '09

Casting of solid slab and topping concrete

Pictures

     

5 Dec '09

First floor column casting

Pictures

     

18 Dec '09

Ground Floor Walls

Pictures

     

30 Dec '09

Preparation for concreting & interior walls

Pictures

     

31 Dec '09

Roof slab & beam casting

Pictures

     

5 Jan '10

Second stage concrete of roof slab

Pictures

     

15 Jan '10

Plastering Work in Progress

Pictures

     

16 Jan '10

Hollow core slabs for 1st Floor

Pictures

     

17 Jan '10

After laying hollow core slabs

Pictures

     

21 Jan '10

Topping of concrete slab

Pictures

     

23 Jan '10

Curing after casting of topping

Pictures

     

27 Jan '10

Exterior Structure & Boundary Wall

Pictures

     

31 Jan '10

Tiling Work in Progress

Pictures

     

5 Feb '10

Boundary wall, plumbing, parapet reinforcement & tiling - Pt 1

Pictures

     

5 Feb '10

Boundary wall, plumbing, parapet reinforcement & tiling - Pt 2

Pictures

     

12 Feb '10

Primer for painting & hollow block work (Ground floor)

Pictures

     

12 Feb '10

Car porch, boundary wall, Service block & Parapet

Pictures

     

22 Feb '10

Tiling, baptistery shuttering & reinforcement, plastering works, hollow works (in progress), wrapping of AC ducts. - Pt 1

Pictures

     

5 Feb '10

Tiling, baptistery shuttering & reinforcement, plastering works, hollow works (in progress), wrapping of AC ducts. - Pt 2

Pictures

     

5 Mar '10

AC duct works and foam concrete for water proofing roof slab

Pictures

     

15 Mar '10

AC duct, baptistery works and waterproofing for the roof

Pictures

     

26 Mar '10

Water proofing, AC ducting & finishing works in progress

Pictures

     

31 Mar '10

Light hollow block, primer painting, front window frame

Pictures

     

6 Apr '10

Stage for Ground & 1st floor, plastering & primer painting

Pictures

     

20 Apr '10

Flooring, Tiling, Painting & External works in progress

Pictures

     

25 Apr '10

Tiling & skirting for the main hall. Primer for service block. Plastering of outside walls. Electrical & AC ducting, Tiling, painting & external works in progress

Pictures

     

28 Apr '10

Roof work, false-ceiling, AC, safety & electrical works in progress

Pictures

     

7 May '10

Terrazo tiles on roof, fire door, painting for walls & tiling

Pictures

     

14 May '10

Foundation for AC units, ceiling frames, toilet tiling & primer painting

Pictures

     

20 May '10

Ceiling frame, infant room, primer painting on outer/inner walls, electrical & firefighting networks, AC ducts works & tiling in main hall in progress

Pictures

     

23 May '10

Staircase at the rear of the building, stage on the first floor, tiling in the main hall, door frames placement etc. in progress

Pictures

     

25 May '10

Internal painting, mock marble sample, block-work above the parapet

Pictures

     

1 Jun '10

Marble laying, AC ducts installation & toilet fittings in progress

Pictures

     

8 Jun '10

Outer Painting & False ceiling on the ground floor

Pictures

     

20 Jun '10

Painting, ceiling works, toilet fittings, outside baptistery in progress

Pictures

     

23 Jun '10

Window frames installation, AC unit installation & bulkhead works in progress

Pictures

     

30 Jun '10

Glass fitting for windows & bulk head work in progress

Pictures

     

27 Jul '10

Rear Staircase flooring, baptistery, pavement flooring & door fitting in progress

Pictures

     

30 Jul '10

Ceiling, hand rail installation, internal & external painting in progress

Pictures

     

6 Aug '10

Painting, AC setup, gate & tank placement along with other finishing works

Pictures

     

12 Aug '10

Tiling, ceiling work, bulk head, AC, painting, gate, front-door works in progress

Pictures

     

16 Aug '10

Electrical lighting fixtures for halls, granite for car porch, painting for borders in progress

Pictures

     

27 Aug '10

AC units installation & tiling of the stage on ground floor in progress

Pictures

     
 Finishing Work

30 Aug '10

Doors fixing, roof tiles painting, ground floor hall tiling in progress

Pictures

     

3 Sept '10

Painting & False ceiling fixing in progress

Pictures

     

5 Sept '10

Pasco, corniche work & 1st floor ceiling work in progress

Pictures

     

13 Sept '10

External painting works for main building & service block in progress

Pictures

     

13 Sept '10

External baptistery preparation, cupboards & 1st floor ceiling finishing in progress

Pictures

     

15 Sept '10

Church name fixed. False ceiling, staircase & cupboard finishing in progress

Pictures

     

23 Sept '10

Ceiling works completed, site-office caravan removed, painting & cleaning in progress

Pictures

     

1 Oct '10

Baptistery works (inside & outside), cupboards works & painting in progress

Pictures

     

8 Oct '10

Front Entrance, cupboards, interior finishing & external painting works in progress

Pictures

     

19 Oct '10

Glass fixing, painting of boundary wall columns, cleaning, cladding of AC in progress

Pictures

     

25 Oct '10

Initial inspection by NAFCO completed successfully for firefighting. Rooms are being cleaned. Painting for boundary wall columns in progress.

Pictures

     

4 Nov '10

Stage Preparation, Sound system cabling & other finishing works in progress.

Pictures

     

10 Feb'11

The First Lights in the BCC - Part 1

Pictures

     

10 Feb'11

The First Lights in the BCC - Part 2

Pictures